Project Overview: The building is a new first-year student residence and dining hall with a student services wing (Learning Commons) that will provide space for administrative, tutoring labs, classrooms and services to support student and faculty success. The building will be located on Larimer Street between 11th and 12th Streets in the CU Denver neighborhood of the Auraria campus.
Project Manager: Phil Friedl – JLL phil.friedl@am.jll.com
Project Architect / Engineer: Stantec/Martin & Martin Engineers
General Contractor: JE Dunn
Gross Square Footage: 175,354 GSF
Project Cost: $78.5M
Project Completion: August 2021
Project Schedule: Feb 2019 – August 2021
Project Overview
Project Updates
5.8.19 Construction Notice - IAQ Testing
4.23.19 Construction Notice - POCs_Rev RM-LS
19_0315 R2 Air Monitoring Summary from EHS
Infiltration Test Report.20190510_with images
URM Workers Compensation Info Letter
Full Trend Data Detailed Reports
Dan Loosbrock CAA ICON dan.loosbrock@caaicon.com
Doug Wilson CAA ICON doug.wilson@caaicon.com
Anderson Mason Dale Architects
JE Dunn Construction
$242,041,741
Construction: 2/2019 2nd Quarter of 2021
223,414
Project Overview
Robert Holzwarth – Facilities Management Projects robert.holzwarth@ucdenver.edu
Architect – Bennett Wagner and Grody Architects (DBA Cannon Design)
M/E/P Engineer – The RMH Group, Inc.
Structural Engineer – Martin/Martin Consulting Engineers
EPA/Air Permitting Consultant – Power Engineers, Inc.
Cost Consultant - Vermeulens
Commissioning Consultant– Group 14 Engineers (pending)
Construction Manager/General Contractor (CMGC) for project is James R. Howell & Co., Inc. (DBA Howell Construction)
Basement 28,328 GSF
First Floor 27,197 GSF
Second Floor 27,197 GSF
Roof 565 GSF
Total 83,287 GSF
$33,398,938
December 2020 (Construction complete, equipment installed and operational)
Pre-Design (Program) August 2018 to November 2018
Design (SD-CD): November 2018 to December 2019
Bid Package 1 – Long Lead Equipment Procurement – Released in February 2019
Long Lead Equipment bids due April 2019
Long Lead Equipment orders placed June 2019
25% Construction Documents issued February 2019
60% Construction Docs (Structural Steel, Chilled Water, Electrical, Architectural) issued May 2019
60% Construction Documents (Steam Systems) issued in July 2019
90% Const. Docs (Structural Steel, Chilled Water, Electrical, Architectural) issued September 2019
100% Constr. Docs (Structural Steel, Chilled Water, Electrical, Architectural) issued October 2019
100% Construction Documents (Steam Systems) issued in November 2019
Construction: November 2019 to December 2020